Construction Update 4/14/2008:
The mass grading crew is making great progress on the site, as the removal of all the remnants of the mining operation continues. The grading crew keeps switching back and forth between the scrappers and rock trucks as they encounter large veins of rocks and boulders that the scrappers struggle to move without damaging the heavy equipment.
The rock trucks and loaders had to be used in this area of the site clean up to remove the larger rocks.

The dozer is used to rip loose bigger boulders so the loader can move it into the back of the rock truck.

The scrappers were back to filling the sub grade with good clean dirt.

The site has changed a lot as the mining operation is removed. It will change even more once the tracks are built..
Warning:
While the mass grading is going on the site is a closed site and no one besides authorized personal will be allowed on site due to the dangerous nature of the construction site. Please do not try and come out to the site, security will not let you through the front gate unless you are chaperoned by a member of the Pala Raceway Staff. Once the mass grading is done and the track building crews are on site we will begin offering site tours.